Efforts

Efforts field is automatically created for tasks when Dependency mode is enabled for a project. It represents the time required to complete a task. You can enter a numerical value for time and select the duration in Days, Weeks, or Months.

Setting up values for Efforts

Efforts_ss_3MSUTJGP0.png
Setting up values for Efforts
  1. Enable Dependency mode for the project. To learn more about Dependency mode, refer to this help article.

  2. Click on the task for which you want to set Efforts.

  3. If Efforts has not been set, click on 0 Day below the Efforts field.

  4. A right panel will open.

  5. Enter a numerical value for Efforts.

  6. Select the duration unit (Days, Weeks, or Months).

  7. Click on Save changes.

How Efforts affect Due dates

To understand dependent and non-dependent tasks better, refer to this help article.

  • For a non-dependent task:

    • If the due date is set to 22/09/2025 and Effort is 2 days, the due date will update to 24/09/2025.

  • For a dependent task:

    • Task A has a due date of 22/09/2025 with Effort of 2 days, so its new due date is 24/09/2025.

    • Task B depends on Task A and no due date is set for Task B. Task B requires an Effort of 3 days.

    • In this case, Task B’s due date will be updated to 27/09/2025.

    To know about Dependency mode, refer to this article.